Client Responsibilities Project Start Highlights
ABN-AMRO
Atlantica
Independent Engineer Atlantica Delta Q4-15 Technical Due Diligence and Acceptance Review
Bondholders Technical Advisor Drillship in Brazil Q3-15 Technical & Operational Management during repossession
Trustee Technical Advisor 3 FPSO's in Brazil Q3-15 Technical & Operational Advice during bankruptcy
Itochu Independent Engineer 5 FPSO's in Brazil Q3-15 Technical Due Diligence and Operational Review
SBM Independent Engineer FPSO Turritella Q2-15 Technical Due Diligence and Operational Review
Bumi Armada Independent Engineer FPSO for Cabaça Q2-15 Technical Due Diligence and Operational Review
GranEnergia Independent Engineer Floatel New build # 3 Q1-15 Technical Due Diligence, acceptance review
"ING Sapura" Independent Engineer 3 x PLSV for Petrobras new build Q4-14 Environmental compliance review
Bumi Armada Independent Engineer AC 7 Q4-14 Technical and performance review
"SMBC Bumi Armada" Independent Engineer FPSO for Kraken Q3-14 Technical Due Diligence, progress monitoring, acceptance review
"SMBC OOG-TK" Independent Engineer EWT FPSO Libra Q4-14 Technical Due Diligence, Environmental compliance review, progress monitoring, acceptance review
GranEnergia Independent Engineer Floatel New build # 2 Q4-14 Technical Due Diligence, acceptance review
QGOG Independent Engineer Drillship Brava Star Q3-14 Technical Due Diligence, Environmental compliance review, progress monitoring, acceptance review
"ABN AMRO SBM" Independent Engineer Deep Panuke USSP Q3-14 Technical and performance review
"ABN AMRO SBM" Independent Engineer FPSO Cd de Maricá Q2-14 Technical Due Diligence, progress monitoring, acceptance review
Nataxis Odebrecht Independent Engineer FPSO for Tartaruga Q2-14 Intial review proposal
Nataxis Petrofac Independent Engineer FPSO Jasmine West Desaru MOPU Q2-14 Technical Due Diligence, compliance review, condition assessment
First Reserve Nataxis Petrofac Independent Engineer FPSO Berantai Q2-14 Technical Due Diligence, compliance review, condition assessment
"ABN AMRO BWO" Independent Engineer FPSO Catcher Q2-14 Technical Due Diligence, progress monitoring, acceptance review
"ABN AMRO SBM" Independent Engineer FPSO Cd de Ilhabela Q2-12 Technical Due Diligence, progress monitoring, acceptance review
OCBC PTSC Independent Engineer FPSO Lam Son Q1-14 Technical Due Diligence, progress monitoring, acceptance review
ING OSX Independent Engineer OSX II Q4-13 Technical Support to banks
ABN AMRO SBM Independent Engineer FPSO for N'Goma Q4-13 Technical Due Diligence, progress monitoring, acceptance review
Clayton Utz Expert witness FPSO Four Rainbow Q4-13 Arbitration matter between ENI and Premuda
ABN AMRO Bass drill Independent Engineer Bass Drill Beta drillship Q3-13 Technical Due Diligence, progress monitoring, acceptance review
Marubeni Independent Engineer Sete Drillships Q3-13 Review yard construction and DRU construction drill ships to be built in Brazil
SMBC M3nergy Independent Engineer FPSO for Bukit Tua Q3-13 Technical Due Diligence, progress monitoring, acceptance review
Delek Navitas Consultancy FLNG projects Q2-13 Technical consultancy, including LNG & Floating Production
Santander GBK Independent Engineer FSRU for Petrobras Q2-13 Technical Due Diligence, progress monitoring, acceptance review
ABN AMRO Ceona Independent Engineer PLV new build Q2 -13 Technical Due Diligence, progress monitoring, acceptance review
SCB Sapura Independent Engineer PLV for Petrobras Q1-12 Environmental compliance review
GranEnergia Independent Engineer Floatel New build Q1-13 Technical Due Diligence, Workability review, progress monitoring, acceptance review
Nataxis Petrofac Independent Engineer FPSO for Berantai Q1-13 Technical review, progress monitoring, acceptance review
Bluewater Independent Engineer FPSO Hæwene Brim, Brynhild Tie-in Q1-13 Technical Review, progress monitoring, acceptance review
OCBC; Bumi
Armada
Independent Engineer FPSO for Balnaves Q4-12 Technical Due Diligence, Environmental compliance review, progress
monitoring, acceptance review
OCBC; PTSC Independent Engineer FSO Vietnam Q4-12 Technical Due Diligence, compliance review
SMBC; MODEC Independent Engineer TEN FPSO Q4-12 Technical Due Diligence, compliance review, progress monitoring
Waterland; JUB Independent Engineer Jack Up Barges Q4-12 Technical Due Diligence, compliance review, condition assessment
Banamex; OSA Independent Engineer 2 Supply & 4 Mud Vessels
for PEMEX
Q4-12 Technical Due Diligence, compliance review, condition assessment
Padre; Chevron Decommissioning study Californian Offshore
facilities
Q1-12 Decomissioning study platforms with PB Consultants
Kennedy Marr;
JUB
Independent Engineer JB 117 Q3-12 Condition assessment
Bumi
Armada
Independent Engineer FPSO for D1 Q2-12 Initial techical review
OSX Independent Engineer FPSO OSX 3 Q2-12 Quick Scan initial project set up
Bumi
Armada
Independent Engineer FPSO for Balnaves Q2-12 Preliminary Techical Due Diligence
ABN AMRO; Nazca Ship Manager Floatel Millennium Q1-12 Ship management during lay up and refurbishment, including contracting
for refurbishment and tender preparation for potential deployment
ABN AMRO; SBM Independent Engineer FPSO Espadarte upgrade Q1-12 General FPSO report, Technical review, progress monitoring, acceptance review
ABN AMRO Independent Engineer Chemical Tankers Q4-11 Technical support
ABN AMRO Independent Engineer Accommodation barges Q4-11 Project Review
BNP; QGOG Independent Engineer SHI Drill ships Q4-11 Environmental compliance review, Technical review, progress monitoring, acceptance review
ABN AMRO Ship Management Floatel Millennium Q3-11 Technical support
SMBC MISC PTSC Independent Engineer FPSO Ruby II Q3-11 Acceptance Confirmation
ABN AMRO Independent Engineer Floatel Millennium Q2-11 Technical support
ING Bank; Bluewater Independent Engineer FPSO Uisge Gorm Q2-11 Compliance Review EnQuest
SMBC & SG TK-OOG Independent Engineer FPSO for Tiro & Sidon Q2-11 Environmental compliance review, Technical review, progress monitoring, acceptance review
ABN AMRO; SBM Independent Engineer FPSO Aseng Q1-11 Environmental compliance review, Technical review, progress monitoring, acceptance review
SMBC Bumi Armada Independent Engineer FPSO for TGT Q1-11 Technical Due Diligence, Environmental compliance review, progress monitoring, acceptance review
ING Bank; OSX Independent Engineer FPSO OSX 2 Q2-11 Technical Due Diligence, Environmental compliance review, progress monitoring, acceptance review
NIBC Bluewater Independent Engineer FPSO Glas Dowr for Kitan field Q4-10 Project review, Technical review, progress monitoring, acceptance review
Deutsche bank; Odebrecht Independent Engineer Norbe VIII & IX Drillships at DSME Q4-10 Progress review, acceptance review and IE during operational phase
SMBC MISC Independent Engineer FSO Orkid Malaysia Q3-10 Perform final acceptance review
Pearl Energy Decommissioning study Jasmine Field Decommissioning Q3-10 Perform decommissioning study for Pearl's Jasmine Field offshore Thailand
Allseas Decommissioning study Brent decommissioning Q2-10 Perform decommissioning study for Shell Brent field
Santander; QGOG Independent Engineer New built SS drill rig Alpha Star Q3-10 Project review, schedule and budget monitoring
Pearl Energy Valuation FPSO Jasmine Venture Q3-10 Determine value of FPSO in several scenario's
Itau bank; Petroserv Independent Engineer New built drill ship at DSME Q3-10 Project review, schedule and budget monitoring
ING Bank; Songa Condition Assessment Condition assessment SS Drill rig Songa Venus offshore Australia Q3-10 Inspect condition and report
ING Bank; Sevan Independent Engineer FPSO Voyageur relocation to Huntington Q3-10 Project review, schedule and budget monitoring
Petro SA Orca Condition Assessment Condition assessment SS FPSO Orca offshore South Afirca Q1-10 Inspect condition and report
HSBC; OOG Independent Engineer ODN 1 & ODN 2 new built drill ships at DSME Q3-10 Project review, schedule and budget monitoring
NIBC; Northern Offshore Fleet Review Review fleet of 1 FPU and 5 offshore drilling units Q1-10 Perform Fleet Technical Review for re-financing
ING Bank; MODEC Quick Scan and Completion review FPSO for Jubilee field Q1-10 Perform quick scan before finance approval and perform Technical Advisor duties during project
ING Bank; Bluewater Quick Scan and Completion review FPSO Glas Dowr relocation Q1-10 Perform quick scan before finance approval and perform Technical Advisor duties during construction phase of project
DownVind Decommissioning study wind park Beatrice wind farm demonstrator Q4-09 Perform decommissioning study find farm UKCS with EU subsidy
Euronav Project management support FSO Asia & Africa conversion Q4-09 Provide project management support for Euronav team on site
BP Prepare scope of work FPSO Schiehallion Q4-09 Prepare scope of work for tender documents for EPC FPSO contract
ING Bank; Bluewater Plan & cost assessment FPSO Munin relocation Q4-09 Verify schedule and cost estimates conversion FPSO for Chinese Project
Euronav Claim assesment FSO Asia & Africa conversion Q4-09 Review claim and variation orders made by yard on behalf of owners
BNP Paribas Invoice verification Norbe VIII & IX Drillships at DSME Q3-09 Review invoices for milestone approval and facility drawdown.
ING Bank; Bluewater Initial cost assessment FPSO Glas Dowr relocation Q2-09 Verify cost estimates conversion FPSO for potential Vietnam Project
NIBC; SBM Full Project review FPSO Capixaba relocation Q2-09 Relocation of FPSO from Capixaba to Cachalote field in Brazil with upgrade in Singapore
NIBC; SBM Full Project review including Equator Principle assessment JUPU Deep Panuke Q2-09 New build jack up production unit for EnCana in Nova Scotia
ING Bank; QGOG Condition Assessment SS Alaskan Star Q2-09 Assess condition operational SS rig, offshore Brazil
Société Générale; Swift Full Project review JUDU Swift Q1-09 Minimum spec New build Jack Up Drilling Rig for SNS
ING Bank; Bluewater Cost and schedule assessment FPSO Aoka Mizu Q1-09 Verify budget and schedule for correction HSE findings
ING Bank; Modec Full Project review FPSO Opportunity/Cidade de Niteroi 2008 Conversion FPSO for Petrobras, Brazil
Hannover Leasing Project review Sea Dragon 2008 Review progress and completion estimates for two new build semi drill rigs
NIBC; Compass Initial project assessment SS Molly Brown, formerly PXIV 2008 Conversion to accommodation semi
Fortis Bank; SBM/MISC Full project review BC-10; Espirito Santo 2008 Conversion FPSO for Shell Brazil
Fortis Bank; MODEC Full Project review FPSO Song Doc 2008 Conversion FPSO for TSJOC Vietnam
ING Bank; SBM Project review FPSO Saxi-Batuque 2008 Exxon Generic E leased FPSO, converted in Singapore, First Oil June 08
Nataxis Floatel Contract review SS Floatel 2008 New build NNS semi Floatel
ING Bank; KSE Acquisition support KS Medstar 2008 Review technical merits prior to potential acquisition JU drill rig
ING Bank; QGOG Progress Review Olinda Star 2008 Conversion & upgrade drilling semi
ING Bank; SBM Project review FPSO Mondo 2007 Exxon Generic D leased FPSO, converted in Singapore, First Oil Dec 07
Technica; ENI Oil Project Management Team FSO Sloug replacement 2007 Provision PMT during tender phase
MPC Delba Project Management SS Delba III 2007 Provision Project Management
ING Bank; SBM Full Project Review FPU Thunder Hawk 2007 New Build FPU for Murphy in GoM
CALYON Technical assessment Olinda Star 2007 Provide technical assessment to support investment decision
NIBC; Sea Jacks Progress Review 2 x lift boats 2007 New build lift boats for North Sea
ABN AMRO; Odebrecht Milestone certification Norbe VI 2007 New build SBM/Gusto DP2 Semisubmersible drill rig
Taqa bv Project management Offshore LNG Terminal 2007 Feasibility study for LNG terminal offshore Rotterdam
Frontier; NIBC Progress & Schedule review Frontier Driller 2007 refurbishment of 1973 Aker H3 semi submersible drill rig
ING Bank; QGOG Technical review Gold Star 2007 New build Keppel/Gusto DP2 Semisubmersible drill rig
ING Bank; QGOG Technical review Lone Star 2007 New build SBM/Gusto DP2 Semisubmersible drill rig
ING Bank; Bluewater Technical review FPSO Aoka Mizu 2007 FPSO for Nexen's Ettrick field; First Oil Q1 2008
Commerz Bank; Premuda Operational review FPSO Four Vanguard 2007 Assess condition and achieved operational uptime;
Wagenborg Managerial support Wagenborg Offshore 2006 Review and adopt management system;
ING Bank; Bluewater Technical review FPSO Aoka Mizu 2006 FPSO for Nexen's Ettrick field; First Oil Q1 2008
ING Bank; SBM Condition assessment LPG FPSO Sanha 2006 Assess repairs and achieved operational uptime;
ING Bank; QGP Technical review 2 x Semi submersible drill rigs 2006 Petrobras leased deepwater semi submersible new build drill rigs; first ops in 2009
Petrojarl Contract review FPSO Siri 2006 Review contract approach for FPSO Siri for Petrobras
Fortis Bank S'pore; SBM Technical review FPSO Kikeh 2006 Murphy Oil Malaysia leased FPSO First Oil Q2 2007
NIBC Bank; SBM Technical review FPSO Capixaba 2006 Petrobras leased FSO, converted in Singapore, First Oil Q2 2006
NIBC; Frontier Project & Technical review Drill semi Explorer 2006 Refurbishment semi submersible drill rig. First ops Q1-09
CBA Bank; Frontline Technical review FPSO Puffin 2006 AED leased FPSO, converted in Singapore, first oil Q3 2007
NAM Shell ITT Documents Sean Compression 2006 Drafting Contract Documents for ITT
Fortis Bank; SBM Offshore Operational review FPSO Espadarte 2006 Petrobras leased FPSO, refinance after 5 year operations offshore Brazil
ING Bank; MODEC Technical review FSO PRA 1 2006 Petrobras leased FSO, converted in Singapore, first oil Q2 2007
ING Bank; Allseas Project & Technical review DP Pipe lay vessel AUDACIA 2006 Conversion to DP Pipe lay vessel. First ops Q1-07
NIBC; Frontier Project & Technical review Drill ship Discoverer 2006 Refurbishment drill ship and upgrade to Arctic environment. First ops Q2-07
CBA Bank; Vanguard Project & Technical review FPSO Puffin 2006 AED leased FPSO, converted in Singapore, first oil Q2 2007
Faegre & Benson; Dresser Rand Quantum expert FPU Janice 2005 Quantum issues on compressors, in court Q2 2006
ING Bank; MODEC Technical review * FPSO Baobab 2005 CNR leased FPSO, converted in Singapore, First Oil May 2005
ING Bank; IHC Caland Technical review * LPG FPSO Sanha 2005 CabGoc leased LPG FPSO, new built in Japan, first Gas February '05
BAE Systems Project management* Decommissioning North Sea range 2005 Project management on behalf of client for complete removal and disposal of 6 North Sea Platforms;
HRAVI; Cumae Quick Scan HR AVI Amsterdam 2004 Quick Scan of EPCI project management for high efficiency waste incineration plant;
Unocal Peer review FPSO development plan 2005 Involved in detailed peer review for alternative field development solutions;
Vermilion Managerial support Onshore assets in Friesland 2004 Supported new team after acquisition;
Contractors Consortium Project Director Q7 Offshore wind park 2004 First offshore wind park in the Netherlands Q7
EMP Cost overrun audit * Melrose Galata field 2004 Determined causes for project overrun
ING Bank; IHC Caland Technical review * FPSO Serpentina 2004 Exxon Generic B leased FPSO, converted in Singapore, First Oil May 2004
ING Bank; IHC Caland Technical review * FPSO Marlim Sul 2004 Petrobras leased FPSO, converted in Singapore, First oil July 2004
ING Bank; IHC Caland Technical review * FPSO Xikomba 2003 Exxon Generic C leased FPSO, converted in Dubai, First Oil Oct 2003
Fortis Bank; IHC Caland Technical review * FPSO Kuito Phase 2A 2002 Chevron Texaco/CabGoc major upgrade executed with FPSO on station. Recommenced production Q1 2003
ING Bank; IHC Caland Technical review * FPSO Falcon 2002 Exxon Generic A leased FPSO, converted in Singapore, First Oil Q4 2002
Vanguard Technical review * FPSO Four Vanguard 2003 Detailed structural and naval architectural review of feasibility of turret design
Soekor PetroSA Schedule Review FPSO Glas Dowr 2003 Progress and remaining work review to establish realistic conversion yard departure date
Fortis Bank; IHC Caland Technical review * FPSO Brasil 2002 Petrobras fast track leased FPSO, replacement for P 36; First Oil Q4 2002
Talisman Project Coordinator FPSO Bleo Holm 2000 Coordinated project for modifying FPSO and addition of gas compressors and water injection facilities. FPSO brought in port and turned around in six weeks;
NIBC Bank; Vanguard Technical review * FPSO Four Vanguard 2002 AGIP Woollybutt field leased FPSO in West Australia, disconnectable turret, construction risk for banks;
Talisman Project Coordinator Bunga Raya 2002 Developed contract strategy and documents for novel re-usable offshore structure MOAB, utilised as fast track compression platform, supervised engineering;
Talisman Offshore Installation 1 GW wind energy park 2002 Prepared input for offshore installation aspects for self-installing wind turbines for EU submission
Fortis Bank; Allseas Market review * Offshore pipe lay market 2001 Review of market opportunities up to 2006 for offshore pipe laying vessels, for corporate finance
Fortis Bank; IHC Caland Technical review * FPSO Espadarte 2001 Petrobras 14 month conversion schedule leased FPSO; First Oil Q3 2001
Herbert Smith; Dresser Rand Quantum expert FPSO North Sea Producer 2001 Arbitration between compressor supplier and FPSO operator;
MeesPierson; IHC Caland Technical review FPSO Kuito phase 1 C 2001 Chevron Texaco/CabGoc upgrade executed with FPSO on station. Recommenced production Q1 2001
Norton Rose; Sembawang Expert Witness Commissioning requirements offshore work vessel 2000 Review of contractual and actual commissioning requirements on a sophisticated offshore construction vessel
BMT marine; Shell Expert Witness Collision 2000 Expert witness on court case resulting after collision between SPM and VLCC in Singapore;
Talisman Project Coordinator Production enhancement Blake 2000 Project manager for fast track study to further increase capacity of process train, during construction phase;
MeesPierson;IHC Caland Technical review FPSO Kuito phase 1 A&B 1999 Chevron/CabGoc leased FPSO, converted in Singapore, First Oil Q4 1999
Bluewater Schedule Review FPSO Bleo Holm 1999 Progress and remaining work review to establish realistic conversion yard departure date

 

Responsibilities indicated with * have been executed jointly with others s.a. Poseidon/Bos-Maritime, Naval Architectural Consultants, OFBS, Bensun consultants and others.